Unit 5: Operations management
5.6 Production planning
Key ideas
- Supply chains move goods from raw materials to customers.
- Just-in-time and just-in-case are opposite approaches to stock.
- Capacity utilization = (actual output ÷ productive capacity) × 100.
Notes
A stock control chart shows the maximum stock level, the reorder level, the buffer stock, the lead time and the reorder quantity. Just-in-case keeps buffer stock to protect against delays.
Productivity can be measured per worker (labour productivity), per machine (capital productivity) or overall (operational productivity). The defect rate measures quality. A make-or-buy decision compares the cost to make internally with the cost to buy from a supplier.
Key terms
- Capacity utilization
- The percentage of maximum possible output that is actually produced.
- Buffer stock
- The minimum stock kept to guard against unexpected demand or delays.
- Lead time
- The time between ordering stock and receiving it.
- Labour productivity
- Output per worker in a period.
Exam practice
A factory can make 50,000 units a month and makes 42,000. Calculate capacity utilization and comment. [3 marks]